Typical Bathroom Remodeling Project Stages

A bathroom remodel runs in a fixed order: consultation and measuring, design and selections, permits or approvals, demolition, rough plumbing and electrical, inspections, waterproofing and testing, tile, fixtures and vanity, glass, then a final walkthrough. Most delays come from the steps that involve someone else, like approvals, inspections and custom glass.

Below is the sequence most projects follow. Every stage depends on the one before, which is why selections made late or approvals that arrive slowly push everything behind them.

  1. Consultation and site visit

    Looking at the room, measuring, checking what's accessible (the attic, the slab, a condo's shared stacks) and talking through what you want to change. This is where early problems show up: soft floors, old cast-iron drains, poor ventilation.

  2. Design and layout

    A layout drawing, sometimes a few options. Decisions about whether fixtures stay put or move, since moving the toilet or shower drain is one of the largest scope changes.

  3. Selections

    Tile, vanity, fixtures, glass style, lighting. Ordering these before demolition is the single most effective way to avoid delays; special-order vanities and some tile series have long lead times.

  4. Quote and schedule

    A written scope and price based on the design and selections, and a start date.

  5. Permits and approvals

    Work that alters plumbing, electrical or structure generally needs a permit from the local building department. Condos add an association approval on top. The paperwork condos ask for is in our condo association guide.

  6. Protection and demolition

    Floors and routes protected, then the room taken back to the studs or concrete. Anything hidden (rot, leaks, old repairs) is found here and discussed before work continues.

  7. Rough-in

    New drain and supply lines, valve bodies, electrical circuits, fan ducting, and blocking for grab bars, glass hinges and floating vanities. Nothing here is visible later, which is why it's the stage to get right.

  8. Rough inspection

    Where a permit is involved, the building department inspects before walls close. Scheduling depends on the inspector's availability.

  9. Walls, board and waterproofing

    Backer board or foam board goes up, then a waterproofing membrane across the shower walls and floor. The shower pan is flood-tested, filled with water for a period to prove it holds. More on this in bathroom waterproofing in South Florida.

  10. Tile

    Usually the longest single stage. Large-format tile needs a flat substrate and more careful handling; mosaics and patterns take longer to lay.

  11. Grout, sealing and paint

    Grout needs curing time before it gets wet. Stone gets sealed. Walls outside the wet area are painted with a moisture-resistant finish.

  12. Fixtures, vanity and lighting

    Vanity and top installed, faucets, toilet, trim kits, lights, mirror and fan connected.

  13. Glass

    Measured after tile is finished, then fabricated and tempered to order. Often the longest wait at the end.

  14. Final inspection and walkthrough

    Final inspection where required, then a walkthrough together to check finish, function and any touch-ups, and hand over care instructions.

How long does each part take?

Every project is different, so here's relative weight instead of a timeline promise:

StageRelative durationWhat stretches it
Design and selectionsVaries mostChanging your mind; long-lead items
Permits and approvalsOutside our controlDepartment backlog; association board meeting schedule
DemolitionShortHidden damage; tile over tile; condo work-hour limits
Rough-in + inspectionModerateMoving drains through a slab; inspection scheduling
Waterproofing + tileLongest on-site stageLarge-format or patterned tile; curing times
GlassWaiting, not workingFabrication lead time after measure

What you'll be asked to decide, and when

  • Before the quote: layout, whether fixtures move, level of finish.
  • Before demolition: every product that is ordered: tile, vanity, valve and trim, toilet, lighting.
  • Before walls close: niche locations, grab-bar blocking, outlet positions, lighting positions.
  • Before tile: tile layout, where cuts land, grout colour.

Condo differences

In a tower, add building-specific steps: association approval, insurance certificates, elevator bookings, restricted work hours and sometimes a notice to neighbours. Our condo bathroom remodeling page explains how those fit into the schedule.

To see what a full scope looks like from start to finish, go to full bathroom remodeling, or read where a remodel budget goes.

Open daily, 7:00 AM to 10:30 PM

Talk to us about your bathroom

Call and tell us about the room: house or condo, what bothers you about it now, and what you'd like it to become. We'll set up a consultation and follow up with a written quote.